* Mid-December monthly on-line review conference using e-conferencing | * Mid-December monthly on-line review conference using e-conferencing | ||
− | * Target date for project completion is Friday, December 14th | + | * Target date for phase 1 project completion is Friday, December 14th |
---- | ---- | ||
==January 2013== | ==January 2013== | ||
− | + | * Start of phase 2 (semantic markup and analysis) | |
− | * Suggested post project completion conference | + | ---- |
+ | ==February 2012== | ||
+ | |||
+ | * Phase 2 (semantic markup and analysis) continues | ||
+ | |||
+ | ---- | ||
+ | ==March 2013== | ||
+ | |||
+ | * Phase 2 (semantic markup and analysis) concludes: | ||
+ | |||
+ | ---- | ||
+ | ==April 2013== | ||
+ | |||
+ | |||
+ | * Suggested post project completion conference (date to be determined closer to planned event) | ||
* Tentatively to be held at the National Archives, Kew (TBC) | * Tentatively to be held at the National Archives, Kew (TBC) | ||
Line 161: | Line 175: | ||
* Suggested invitees: all project team members and selected guests | * Suggested invitees: all project team members and selected guests | ||
− | * [[Conference | + | * [[Conference April 2013 discussion page|Conference April 2013 discussion page]] |
− | + | ||
[[Comments]] | [[Comments]] | ||
------ | ------ | ||
''2012-08-16 11:41:22'' [[nbsp]] Thanks Jill for spotting the unusual chronology of January 2012 coming after December 2012. I have now corrected this to 2013 --[[Users/ColinGreenstreet|Users/ColinGreenstreet]] | ''2012-08-16 11:41:22'' [[nbsp]] Thanks Jill for spotting the unusual chronology of January 2012 coming after December 2012. I have now corrected this to 2013 --[[Users/ColinGreenstreet|Users/ColinGreenstreet]] |
Revision as of 07:06, September 27, 2012
Monthly Schedule
Editorial history
08/08/12: SL, created page
Contents
- 1 Team member availability register
- 1.1 Associates
- 1.1.1 Katie Broke
- 1.1.2 Alex Calvo
- 1.1.3 Ian Cowley
- 1.1.4 Dr Janet Few
- 1.1.5 Karen Gunnell
- 1.1.6 Emma Hardy
- 1.1.7 Dr Liam Haydon
- 1.1.8 William Kellett
- 1.1.9 John Miller
- 1.1.10 David Pashley
- 1.1.11 Dr Cathryn Pearce
- 1.1.12 Giovanna Rampone
- 1.1.13 Marta Rezzano
- 1.1.14 Daniel Richards
- 1.1.15 Laura Seymour
- 1.1.16 Ida Sjoberg
- 1.1.17 Gordon O'Sullivan
- 1.1.18 Tommy Walters
- 1.2 Team facilitators
- 1.3 Advisors
- 1.1 Associates
- 2 August 2012
- 3 September 2012
- 4 October 2012
- 5 November 2012
- 6 December 2012
- 7 January 2013
- 8 February 2012
- 9 March 2013
- 10 April 2013
Team member availability register
Please enter any dates that you are NOT available during the period September 3rd to December 14th under your name below:
Associates
Katie Broke
Alex Calvo
Ian Cowley
Dr Janet Few
21 Sept - 9 Oct
Karen Gunnell
Emma Hardy
Dr Liam Haydon
William Kellett
John Miller
David Pashley
Dr Cathryn Pearce
Giovanna Rampone
Marta Rezzano
Daniel Richards
Laura Seymour
Ida Sjoberg
Gordon O'Sullivan
Tommy Walters
Team facilitators
Giovanni Colavizza (facilitator and technical advisor)
September: 7,8,15-17
Colin Greenstreet
Tuesday October 2nd, mornimg and afternoon unavailable
Patrizia Rebulla
William Tullett
Jill Wilcox
Advisors
Richard Blakemore
Dr Catherine Buchanan
Dr Stuart Dunn
Dr Charlene Eska
Jo Pugh
Margaret Schotte
August 2012
August 1st to 31st
- Train facilitators and advisors online
- Work with facilitators to prepare online training material for associates
- Dr Charlene Eska working with Colin Greenstreet, with input from Dr Elaine Murphy, on transcription and editorial policy. A draft document will be shared and discussed at the August 20th face-to-face meeting
- Project leader & facilitators to create a digital backbone for the project, with all images checked for quality and readability, and meta data created and input into the chosen document platform (post August 20th & by September 3rd, following agreement at August 20th meeting on specific volume to digitise and transcribe)
- Giovanni Colavizza (our project technical advisor) to implement chosen technology solution, in coordination with Colin Greenstreet and Dr Stuart Dunn, prior to September 3rd, with sufficient time for testing system and the training of facilitators on the system
August 20th
- Face-to face one day meeting at TNA (August 20th) to look and feel the documents we will be working on, to meet TNA staff, and to practice technical and palaeographical skills. This meeting to consist of project facilitators, advisors, and those project associates who are available
- Jo Pugh (TNA) is exploring whether web conferencing or dial-in TC facilities can be arranged
- Dr Charlene Eska has asked whether the palaeography training session could be recorded and made available in the online MarineLives Project Manual. Colin is to ask Giovanni Colavizza to look into the technical capability of either the MarineLives wiki or the MarineLives website to support video clips
- Ideas requested from team members for the draft agenda on August 20th:
See Kick Off Meeting 20 August discussion page
September 2012
Week of September 3rd
- Online training of project associates directed and supported by facilitators
Week of September 10th
- Allocation of facilitators to project associates
- Kick off transcription work
Friday, September 28th (TBC)
- First monthly on-line review conference using e-conferencing
- Process and arrangements to be discussed at August 20th face-to-face meeting, and confirmed in September, once transcription work is underway
October 2012
- Continuing transcription work
- Five new project associates start on October 1st with a week of training
- Start of four weeks of interviews with external academics and PhD forum to get input to proposed TEI-compliant semantic mark-up schema
- End October monthly on-line review conference using e-conferencing
November 2012
- Continuing transcription work and beginning of linkage and enrichment work
- End November monthly on-line review conference using e-conferencing
December 2012
- Concluding linkage and enrichment work, and datamining of text
- Mid-December monthly on-line review conference using e-conferencing
- Target date for phase 1 project completion is Friday, December 14th
January 2013
- Start of phase 2 (semantic markup and analysis)
February 2012
- Phase 2 (semantic markup and analysis) continues
March 2013
- Phase 2 (semantic markup and analysis) concludes:
April 2013
- Suggested post project completion conference (date to be determined closer to planned event)
- Tentatively to be held at the National Archives, Kew (TBC)
- Suggested invitees: all project team members and selected guests
2012-08-16 11:41:22 nbsp Thanks Jill for spotting the unusual chronology of January 2012 coming after December 2012. I have now corrected this to 2013 --Users/ColinGreenstreet